Continued Construction

Hello,

The following should shed some light on the planned construction schedule for the upcoming weeks.

This round of construction began in December and as January comes to a close, the renovation work in the hotel continues, as it will for a while into February.

Even though we are running a little behind schedule, we predict that our new lift, reception area and tv lounge will be completed by the 11th of February, and then shortly after, our new conservatory will be finished on the 18th.

We thank everybody who has visited during this period and to those of you who have left such encouraging words on the website, we hope that the remaining work will go as swiftly and quietly as it is now and that it will make a big difference as we reopen our new and improved hotel and restaurant.

-Dukes Folly Hotel